Re: OPTIMIZATION THEORY
Posted by Anonymous on 2007/3/13 10:33:35
Thanks Tim.
I'll give it another try by compressing the document ...
SOLUTION TO OPTIMIZATION THEORY
20 x 5.1m sawn into
LARGE SIZE
20 x 1.99m = 39.8m
20 x 1.33m = 26.6m
MEDIUM SIZE
08 x 1.755m = 14.04m
04 x 0.985m = 3.94m
SMALL SIZE
08 x 1.700m = 13.6m
04 x 0.765m = 3.06m
Wastage : 0.96m
---------------------------------------------------
08 x 5.1m sawn into
LARGE SIZE
16 x 2.035m = 32.56m
MEDIUM SIZE
08 x 0. 89m = 7.12m
SMALL SIZE
- nil -
Wastage : 1.12m
---------------------------------------------------
02 x 5.1 sawn into
LARGE SIZE
04 x 2.35m = 8.14m
MEDIUM SIZE
- nil -
SMALL SIZE
02 x 0.67m = 1.34m
Wastage : 0.72m
--------------------------------------------------
04 x 5.1m sawn into
LARGE SIZE
10 x 1.425m = 14.25m
- nil -
MEDIUM SIZE
- nil -
- nil -
SMALL SIZE
02 x 1.655m = 3.31m
02 x 0.670m = 1.34m
Wastage : 1.5m
---------------------------------------------------
07 x 5.1m sawn into
LARGE SIZE
- nil -
- nil -
MEDIUM SIZE
08 x 1.8m = 14.4m
- nil -
SMALL SIZE
06 x 1.655m = 9.93m
04 x 0.670m = 2.68m
Wastage : 8.69m
---------------------------------------------------
Summary:
41 x 5.1m = 209.10m
Large Size uses = 121.35m
Medium Size uses = 39.50m
Small Size uses = 35.26m
---------------------------------------------------
Total Usage = 196.11m
Wastage = 12.90m
---------------------------------------------------
% Wastage = 12.90/209.10x100
= 6.212339%
===================================================
This Post was from: http://okenglish.tw/newbb/viewtopic.php?forum=3&topic_id=1679&post_id=5593